Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is 1. The detailed process requirements are published in Part 1 of CAP 1616.

London Stansted Airport wishes to modernise airs pace arrangements for aircraft operating to and from the Airport at altitudes of 7,000 feet and below. In 2017, London Stansted introduced performance based navigation to two existing departure routes . The Airport now seeks to make further us e of the new technologies so that the operational efficiency and environmental benefits that modern aircraft offer can now be fully realised. In so doing, the optimised procedures that will be

developed will integrate fully with other airports and the wider changes to the airspace system and remove the Airport’s reliance on ground based navigational aids .

Close

Step 3a : Consultation Preparation

This step has been started

During the Consultation Preparation Step, the sponsor plans its stakeholder consultation and engagement, and prepares consultation documents, including the second-phase Full options appraisal with more rigorous evidence for its chosen option(s).

Documents for this proposal (51 documents)

Initial Options Appraisal Assessment

Step 2b - Options Appraisal Assessment (Phase I - Initial)

Date added: 13 April 2022

London Stansted Stage 2 CAA Request Clarification

Develop & Assess Gateway - Other

Date added: 11 April 2022

Initial Options Appraisal Report (IOA) - V2

Develop & Assess Gateway - Other

Date added: 11 April 2022

Design Principle Evaluation (DPE) - V2

Develop & Assess Gateway - Other

Date added: 11 April 2022

Design Options Report (DOR) - V2

Develop & Assess Gateway - Other

Date added: 11 April 2022

Stage 2 Summary Document - V2

Develop & Assess Gateway - Other

Date added: 11 April 2022

Stage 2 Summary Document Appendix A - Design Options Evolution

Develop & Assess Gateway - Other

Date added: 11 April 2022

Stage 2 Summary Document

Develop & Assess Gateway - Engagement Evidence

Date added: 10 March 2022

Initial Options Appraisal Report (IOA)

Step 2b - Options Appraisal Assessment (Phase I - Initial)

Date added: 07 March 2022

IOA Appendix A Full Analysis Table

Step 2b - Options Appraisal Assessment (Phase I - Initial)

Date added: 07 March 2022

Design Principles Evaluation (DPE)

Step 2a - Design Principle Evaluation

Date added: 07 March 2022

Design Options Report (DOR)

Step 2a - Design Options

Date added: 07 March 2022

Stakeholder Engagement Report (SER)

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 1 Full List Of Stakeholders Engaged

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 2 Chronology Of Engagement

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 3 Phase One Engagement Materials

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 4 Phase Two Engagement Departures Material

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 5 Phase Two Engagement Arrivals Material

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 6 YouGov Phase One Forums Feedback Report

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 7 YouGov Phase Two Focus Groups Feedback Report

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 8 Phase One Discussion Sessions Feedback Report

Step 2a - Engagement Evidence

Date added: 07 March 2022

SER Appendix 9 Phase Two Discussion Sessions Feedback Report

Step 2a - Engagement Evidence

Date added: 04 March 2022

SER Appendix 10 Phase Two General Public Survey Feedback Report

Step 2a - Engagement Evidence

Date added: 04 March 2022

SER Appendix 11 Summary of Feedback Responses and Q&A

Step 2a - Engagement Evidence

Date added: 04 March 2022

SER Appendix 12 tCI Statement of Assurance

Step 2a - Engagement Evidence

Date added: 04 March 2022

Indicative Timeline - July 2021

Step 2a - Timeline Agreement

Date added: 09 July 2021

ACP Revised Timeline V3

Step 2a - Timeline Agreement

Date added: 05 January 2021

Appendix 9 - Summary of Stakeholder Comments V2

Step 1b - Design Principles Engagement Evidence

Date added: 04 August 2020

Design Principles Report V2

Step 1b - Design Principles Engagement Evidence

Date added: 04 August 2020

Appendix 13 - Additional Engagement Material

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 12 - Phase 2 Engagement- Online Workshops

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 11 - Phase 1 Engagement - Online Portal

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 10 - Phase 1 Engagement - Focus Groups

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 9 - Summary of Stakeholder Comments

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 8 - tCI Quality Assurance Report

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 7 - Stakeholder Reference Group - ToR

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 6 - Press Releases

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 5 - Internal Communications

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 4 - Email to Stakeholders

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 3 - Chronology of Engagement Activity

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 2 - Full List of Stakeholders Engaged

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Appendix 1 - Engagement Document

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

Design Principles Report

Step 1b - Design Principles Engagement Evidence

Date added: 03 July 2020

ACP Revised Timeline V2

Step 1b - Other

Date added: 07 January 2020

Letter to Sponsor from CAA Airspace Modernisation

Step 1b - Other

Date added: 05 August 2019

ACP Revised Timeline

Step 1b - Other

Date added: 28 June 2019

Statement of Need v1

Step 1a - Statement of Need

Date added: 27 February 2019

Assessment Meeting Minutes

Step 1a - Assessment Meeting Minutes

Date added: 18 February 2019

Assessment Meeting Presentation

Step 1a - Other

Date added: 18 February 2019

Assessment Meeting Agenda

Step 1a - Assessment Meeting Agenda

Date added: 18 February 2019

Close

Potentially affected area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Close

Back to previous page