Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is TBC.

Further modernisation of the airspace structure in the North Wales and Irish Sea Area to accommodate forecast demand and to align with CAA Airspace Modernisation Strategy

Close

Step 2a : Develop & Assess

This step has been started

During the Options Development Step, the change sponsor develops one or more design options that address the Statement of Need and align with the defined design principles.

CAA response to Step 2a

25/10/2019 - The CAA has completed the Define Gateway Assessment on 25 Oct 19 and is not satisfied that the change sponsor has met the requirements of the Process up to this point. The CAA does not approve progress to the next Step.

29/11/2019 - The CAA accepts the process and approach used to develop the design principles and accepts that they represent a well-founded shortlist to inform the development of design options.

Close

Documents for this proposal (15 documents)

Timeline Change Approval (136.0kB PDF)

Step 2a - Other

Date added: 27 February 2020

Y124 Stage 2Ai Design Options v1.0 (withdrawn) (3.9MB PDF)

Step 2a - Design Options

Date added: 27 February 2020

Y124 Stage 2B Options Appraisal (Initial) V1.0 (404.6kB PDF)

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 14 February 2020

Y124 Stage 2Aii Design Principles Eval v1.0 (309.9kB PDF)

Step 2a - Design Principle Evaluation

Date added: 14 February 2020

Timeline Change Approval (136.0kB PDF)

Step 2a - Other

Date added: 02 January 2020

Y124 Design Principles Document V2.1 (856.2kB PDF)

Step 1b - Design Principles

Date added: 04 December 2019

Y124 Design Principles Document V2.0 (748.0kB PDF)

Step 1b - Design Principles Engagement Evidence

Date added: 18 November 2019

Y124 Revised Timelines (186.7kB PDF)

Step 1b - Other

Date added: 11 November 2019

Y124 Design Principles Document V1.2 (1.1MB PDF)

Step 1b - Other

Date added: 21 October 2019

Y124 Design Principles Document V1.1 (831.5kB PDF)

Step 1b - Design Principles Engagement Evidence

Date added: 16 October 2019

Y124 Design Principles Document V1.0 (800.0kB PDF)

Step 1b - Design Principles Engagement Evidence

Date added: 11 October 2019

Y124 Assessment Meeting Presentation (2.0MB PDF)

Step 1a - Other

Date added: 07 May 2019

Y124 Assessment Meeting Minutes (329.2kB PDF)

Step 1a - Assessment Meeting Minutes

Date added: 07 May 2019

Assessment meeting agenda (564.9kB PDF)

Step 1a - Assessment Meeting Agenda

Date added: 24 April 2019

Y124 Statement of Need (ref 2533) (1.0MB PDF)

Step 1a - Statement of Need

Date added: 04 March 2019