Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is 0.

In July 2019 Gatwick Airport Ltd (“GAL”) announced its intention to prepare a planning application (Development Consent Order (DCO)) to bring into operation the routine use of its runway 08L/26R at the same time as its runway 08R/26L.

To enable dependent dual runway operations, it is proposed that the runway centreline datum of runway 08L/26R be re-positioned 12m northwards to ensure the required centreline spacing from runway 08R/26L.

When operating in dual runway mode it is estimated that code C or smaller aircraft would routinely take off from the re-positioned 08L/26R runway. Consequently the initial track of these air traffic movements would be 210 m further to the north.

It is assessed that dual runway operations would be operated using existing SID, STAR and IAPs.

Since above change requires minor modifications to the airport’s Aeronautical Information Publication (AIP) entry, GAL is requesting an assessment meeting with the CAA as per Stage 1A of CAP1616.

Close

Step 6 : Implement

This step has been started

During the Implement Step, the change sponsor implements the approved change, working with air navigation service providers as necessary.

CAA response to Step 6

CAA statement

19/11/2025: Due to the impact of COVID-19 and an ongoing legal challenge, the target AIRAC date for ACP-2019-81 has been revised to AIRAC 09/2027, with an effective date of 02 September 2027.

Close

Documents for this proposal (5 documents)

ACP-2019-81 Assigned Level Decision (CAP 1908) (237.6kB PDF)

Step 1 - Final Regulatory Decision

Date added: 07 May 2020

Northern Runway Assessment Meeting Presentation (508.8kB PDF)

Step 1 - Other

Date added: 07 May 2020

Northern Runway Assessment Meeting Minutes (168.9kB PDF)

Step 1 - Assessment Meeting Minutes

Date added: 07 May 2020

Northern Runway Project Agenda (68.1kB PDF)

Step 1 - Assessment Meeting Agenda

Date added: 03 January 2020

Northern Runway Project Statement of Need (550.3kB PDF)

Step 1 - Statement of Need

Date added: 16 December 2019