Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is TBC.

ACP-2021-078 described a requirement for segregated airspace to facilitate RPA operations from RAF Fairford, including climb/descent for HALE and MALE RPAs and onward transit for MALE RPAs. The complexity introduced by medium-level transit corridors threatened to delay the entire project, therefore the decision has been made to split the ACP into separate HALE and MALE elements. This new ACP aims to establish suitable segregated airspace to enable MALE RPA transition between RAF Fairford and the FIR boundaries.

Close

Develop and Assess Gateway

This step has been started

At the Develop and Assess Gateway, the CAA completes a regulatory assessment of the change sponsor's outputs and relevant supporting evidence to determine whether the airspace change process requirements of Stage 2 have been followed.

Documents for this proposal (23 documents)

ACP Split Explanation Letter (76.2kB PDF)

Develop and Assess Gateway - Engagement Evidence

Date added: 11 November 2022

Agreed Timeline Change (179.5kB PDF)

Develop and Assess Gateway - Timeline Agreement

Date added: 10 November 2022

Stage 2 Gateway Action - Clarification Letter (35.6kB PDF)

Develop and Assess Gateway - Other

Date added: 10 November 2022

2B Initial Options Appraisal (2.3MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 10 November 2022

2A Design Principle Evaluation (3.5MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 10 November 2022

Meeting Minutes - NATS (40.3kB PDF)

Stage 2 - Engagement Evidence

Date added: 10 November 2022

Meeting Minutes - London Oxford Airport (113.8kB PDF)

Stage 2 - Engagement Evidence

Date added: 10 November 2022

Meeting Minutes - VOWH (113.2kB PDF)

Stage 2 - Engagement Evidence

Date added: 10 November 2022

Meeting Minutes BGA (113.1kB PDF)

Stage 2 - Engagement Evidence

Date added: 10 November 2022

Stakeholder Engagement Feedback (12.3MB PDF)

Stage 2 - Design Options Engagement Evidence

Date added: 10 November 2022

Stage 2A Feedback Form (65.7kB PDF)

Stage 2 - Design Options Engagement Evidence

Date added: 10 November 2022

Stage 2A Initial Options Engagement Letter (1.1MB PDF)

Stage 2 - Design Options Engagement Evidence

Date added: 10 November 2022

Stage 1 Submission V2 (1.3MB PDF)

Stage 1 - Design Principles

Date added: 08 November 2022

Oxfordshire RAUWG Minutes - 9 Mar 22 (316.8kB PDF)

Stage 1 - Engagement Evidence

Date added: 08 November 2022

Oxfordshire RAUWG Presentation (807.0kB PDF)

Stage 1 - Engagement Evidence

Date added: 08 November 2022

Stage 1 Submission (2.2MB PDF)

Stage 1 - Design Principles

Date added: 08 November 2022

Engagement Local Authorities (160.0kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 08 November 2022

Engagement Airspace Users (201.8kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 08 November 2022

Timeline Change (180.9kB PDF)

Stage 1 - Timeline Agreement

Date added: 08 November 2022

Assessment Meeting Minutes (184.3kB PDF)

Stage 1 - Assessment Meeting Minutes

Date added: 08 November 2022

Assessment Meeting Presentation (369.1kB PDF)

Stage 1 - Other

Date added: 08 November 2022

Assessment Meeting Agenda (46.7kB PDF)

Stage 1 - Assessment Meeting Agenda

Date added: 08 November 2022

Statement of Need (88.5kB PDF)

Stage 1 - Statement of Need

Date added: 08 November 2022