Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is M2.

In order to meet the complex training objectives of Defence during Ex Joint Warriors, a large scale multi-national military exercise, segregated airspace is required that:

• Is within reach of Navy Forces, more specifically a Carrier Strike Group (with embarked 5th generation air systems) operating within Deep Water, which through the development of the scenario is likely to span hundreds of miles.

• Provides a sufficient mixture of overland and overseas areas which offers exercise planners flexibility to create more complex scenarios across both environments, for necessary littoral operations.

• Crucially caters for kinetic and non-kinetic ranges within the area, which allows for necessary Air Land integration.

• Is of large enough size to accommodate representative operational numbers.

In order for UK Danger Areas to comply with both the UK’s Airspace Modernisation Strategy and incoming Free Route Airspace (FRA), every danger area requires a “parent” danger area in the UK AIP in order for Flight Buffer Zones to be applied and thus enable FRA. In an increasingly busy UK airspace, segregated airspace of a large enough size and in a suitable location will not exist after FRA is implemented and current solutions are untenable to deliver the required needs of Defence.

Close

Decide Gateway

This step has been started

At the Decide Gateway, the CAA reviews and signs-off the documentation relating to Stage 5.

CAA response to Decide Gateway

The CAA has completed the Decide Gateway Assessment and is satisfied that the change sponsor has met the requirements of the Airspace Change Process. The CAA approves the implementation of this airspace change proposal for the reasons set out in the regulatory decision document.

Close

Documents for this proposal (28 documents)

Stage 5 Operational Assessment (286.1kB PDF)

Decide Gateway - Other

Date added: 19 June 2023

Regulatory Decision Document (274.4kB PDF)

Decide Gateway - Gateway Decision

Date added: 14 June 2023

Stage 5 Final Options Appraisal Assessment (877.0kB PDF)

Decide Gateway - Other

Date added: 14 June 2023

Stage 5 Environmental Assessment (661.2kB PDF)

Decide Gateway - Other

Date added: 14 June 2023

Stage 5 Consultation Assessment (295.2kB PDF)

Decide Gateway - Other

Date added: 14 June 2023

Stage 5 Safety Review (427.6kB PDF)

Decide Gateway - Other

Date added: 14 June 2023

Stage 5 ATM Safety Review CAA Letter of Acceptance (142.6kB PDF)

Decide Gateway - Other

Date added: 14 June 2023

Full Options Appraisal Assessment V2.1 (282.6kB PDF)

Step 3b - Options Appraisal Assessment (Phase II - Full)

Date added: 06 December 2022

Revised Timeline (116.2kB PDF)

Step 3a - Timeline Agreement

Date added: 09 November 2022

Initial Options Appraisal Assessment (981.0kB PDF)

Step 2b - Options Appraisal Assessment (Phase I - Initial)

Date added: 31 May 2022

Stage 2B Options Appraisal (506.4kB PDF)

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 15 May 2022

Stage 2A Design Principle Evaluation (199.0kB PDF)

Step 2a - Design Principle Evaluation

Date added: 15 May 2022

Stage 2A Engagement Summary (121.6kB PDF)

Step 2a - Engagement Evidence

Date added: 15 May 2022

Stage 2A Engagement Evidence (793.0kB PDF)

Step 2a - Engagement Evidence

Date added: 15 May 2022

Stage 2A Options Development (682.7kB PDF)

Step 2a - Design Options

Date added: 15 May 2022

Indicative Timeline - April 2022 (178.2kB PDF)

Step 2a - Timeline Agreement

Date added: 20 April 2022

Stage 1B Design Principles Submission v2.0 (261.4kB PDF)

Step 1b - Design Principles Engagement Evidence

Date added: 21 December 2021

Minutes of Draft Design Principals Meeting with NATS and DAATM (131.3kB PDF)

Step 1b - Engagement Evidence

Date added: 17 December 2021

Stage 1B Engagement Responses (474.8kB PDF)

Step 1b - Engagement Evidence

Date added: 07 December 2021

Stage 1B Design Principles Submission (254.5kB PDF)

Step 1b - Design Principles Engagement Evidence

Date added: 07 December 2021

Engagement Letter (177.6kB PDF)

Step 1b - Engagement Evidence

Date added: 07 December 2021

Engagement Covering Email (71.0kB PDF)

Step 1b - Engagement Evidence

Date added: 07 December 2021

Timeline Agreement (179.0kB PDF)

Step 1b - Timeline Agreement

Date added: 07 December 2021

Assessment Meeting Presentation (175.1kB PDF)

Step 1a - Other

Date added: 03 December 2021

Assessment Meeting Minutes (160.0kB PDF)

Step 1a - Assessment Meeting Minutes

Date added: 03 December 2021

Assessment Meeting Agenda (126.6kB PDF)

Step 1a - Assessment Meeting Agenda

Date added: 10 August 2021

Statement of Need v2 (137.0kB PDF)

Step 1a - Statement of Need

Date added: 19 July 2021

Statement of Need v1 (122.3kB PDF)

Step 1a - Statement of Need

Date added: 19 July 2021

Close

Potentially affected area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Close