Southampton Airport

Southampton International Airport ACP under FASI-S
IN PROGRESS

ID: ACP-2019-03

This proposal is for a Permanent airspace change, and is level TBC.
Created: 29 January 2019
Last updated: 03 September 2019

Four in total ACP engagement workshops have taken place on the 28th of June, 1st 19th and 23rd of July.


Step 2a : Develop & Assess - This step has been started

During the Develop & Assess Step, the change sponsor develops one or more options that address the Statement of Need and align with the defined design principles.



Have a question? Click here to contact Southampton Airport
Receive email updates about this airspace change

Please note this form is protected by reCAPTCHA.


View news about this airspace change

Purpose of this change

The Department for Transport have notified aviation stakeholders that the controlled airspace in southern England used to support commercial air transport operations is capacity constrained. Passenger delays are expected to increase sharply over the next ten years if the airspace structure and route network are not upgraded to introduce additional capacity. The Future Airspace Strategy Implementation South (FASI South) programme has been established by NATS and fifteen key airports operating in southern England, including Southampton Airport Ltd. to coordinate a series of linked ACPs that will modernise the overall airspace structure and route network.

Potentially Affected Area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Documents for Step 2a : Develop & Assess


The CAA Response


Let us know your thoughts on this current step of this proposed airspace change.

Closing Date:
Provide Feedback