Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is TBC. The detailed process requirements are published in Part 1 of CAP 1616.

Gatwick Airport is now undertaking a new airspace change proposal involving a review and if appropriate redesign of the Route 4 SIDs taking into account the relevant aspects of the Consent Order

CAA response to Step 2a

28/02/2020: The CAA does not approve the Design Principal Evaluation submitted by the sponsor.

Documents for this proposal (36 documents)

Gateway Outcome

Develop & Assess Gateway - Develop & Assess Gateway outcome

Date added: 28 February 2020 16:07

MINUTES 3 MAR 2020 MEETING

Step 2b - Other

Date added: 12 August 2020 11:33

Timeline Update

Step 2b - Timeline Agreement

Date added: 17 July 2020 11:21

Initial Options Appraisal Table Issue 1

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 18 February 2020 14:19

Initial Options Appraisal Issue 1

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 18 February 2020 14:19

Indicative Timeline Update - October 2021

Step 2a - Timeline Agreement

Date added: 04 November 2021 13:01

Minutes 3 Feb 21 Meeting

Step 2a - Other

Date added: 27 April 2021 11:56

GAL Letter Seeking CAA Response – Stage 2

Step 2a - Other

Date added: 16 April 2021 12:26

Indicative Timeline Update March 2021

Step 2a - Timeline Agreement

Date added: 06 April 2021 11:04

Focus Group 1 and 2 Presentations

Step 2a - Other

Date added: 20 February 2020 10:29

Focus Group 2 Feedback

Step 2a - Additional stakeholder feedback

Date added: 20 February 2020 10:28

Focus Group 1 Feedback

Step 2a - Additional stakeholder feedback

Date added: 20 February 2020 10:28

Focus Group 1 and 2 Minutes

Step 2a - Additional meeting minutes

Date added: 20 February 2020 10:27

Options Development Stage 2 Issue 1

Step 2a - Design Principle Evaluation

Date added: 18 February 2020 14:18

Design Principles Evaluation Issue 1

Step 2a - Design Principle Evaluation

Date added: 18 February 2020 14:15

Indicative Timeline Update Jan 2020

Step 2a - Airspace Change Proposal

Date added: 24 January 2020 14:48

Indicative Timeline Update Dec 2019

Step 2a - Other

Date added: 19 December 2019 16:22

Design Principles Review - Responses

Step 1b - Design Principles Engagement Evidence

Date added: 24 September 2019 10:32

Design Principles Questionnaires - Responses

Step 1b - Design Principles Engagement Evidence

Date added: 24 September 2019 10:30

Focus Group 3 Minutes - redacted

Step 1b - Additional meeting minutes

Date added: 13 September 2019 10:16

Focus Group 2 Minutes - redacted

Step 1b - Additional meeting minutes

Date added: 13 September 2019 10:15

Focus Group 1 Minutes - redacted

Step 1b - Additional meeting minutes

Date added: 13 September 2019 10:15

Design Principles Review Response Document

Step 1b - Design Principles Engagement Evidence

Date added: 13 September 2019 10:12

Design Principles Review

Step 1b - Design Principles Engagement Evidence

Date added: 13 September 2019 10:11

Design Principles Questionnaires Introduction

Step 1b - Design Principles Engagement Evidence

Date added: 13 September 2019 10:10

Design Principles Focus Groups Presentation

Step 1b - Design Principles Engagement Evidence

Date added: 13 September 2019 10:09

Design Principles Report Issue 1

Step 1b - Design Principles Engagement Evidence

Date added: 13 September 2019 09:59

Gateway Dates

Step 1b - Other

Date added: 28 August 2019 15:34

Gateway Dates

Step 1b - Additional meeting minutes

Date added: 02 May 2019 10:27

Response Letter from CAA to Gatwick

Step 1a - Other

Date added: 08 July 2019 11:07

Response Letter from Gatwick to CAA

Step 1a - Other

Date added: 08 July 2019 11:05

CAA Letter to Gatwick

Step 1a - Other

Date added: 14 June 2019 13:20

Assessment Meeting Presentation

Step 1a - Additional meeting minutes

Date added: 07 February 2019 14:51

Assessment Meeting Minutes

Step 1a - Assessment Meeting Minutes

Date added: 07 February 2019 14:51

Assessment Meeting Agenda

Step 1a - Assessment Meeting Agenda

Date added: 23 January 2019 13:32

Statement of Need v1

Step 1a - Additional meeting minutes

Date added: 19 December 2018 15:25

Close

Potentially Affected Area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Step 2a : Develop & Assess

This step has been started

During the Options Development Step, the change sponsor develops one or more design options that address the Statement of Need and align with the defined design principles.