Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is 1.

Gatwick Airport is now undertaking a new airspace change proposal involving a review and if appropriate redesign of the Route 4 SIDs taking into account the relevant aspects of the Consent Order

Close

Stage 3 : Consultation/Engagement Preparation

This step has been started

At the beginning of Stage 3 the change sponsor prepares a strategy and draft materials and submits them to the CAA, along with the full options appraisal.

CAA response to Stage 3

18th January 2024:

The revised airspace change process (CAP 1616, Version 5) will be implemented on 02 January 2024. This ACP will remain a Level 1 and will need to follow the process requirements as set out in CAP 1616 Version 5 for its scheduled Gateway in March 2024.

Close

Documents for this proposal (55 documents)

Timeline Update (121.9kB PDF)

Stage 3 - Timeline Agreement

Date added: 09 September 2024

Timeline update (206.7kB PDF)

Stage 3 - Timeline Agreement

Date added: 20 March 2024

Timeline update (120.0kB PDF)

Stage 3 - Timeline Agreement

Date added: 04 March 2024

ACP Timeline Update (182.0kB PDF)

Stage 3 - Timeline Agreement

Date added: 11 July 2023

Initial Options Appraisal Assessment (272.4kB PDF)

Stage 2 - Options Appraisal Assessment (Phase I - Initial)

Date added: 31 October 2022

Initial Options Appraisal Appendix Submission 2 Issue 2 (162.6kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 26 October 2022

Initial Options Appraisal Submission 2 Issue 2 (2.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 26 October 2022

Design Principles Evaluation Submission 2 Issue 2 (8.2MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 26 October 2022

ACP-2018-86 Indicative Timelines Request September 22 (182.4kB PDF)

Stage 2 - Timeline Agreement

Date added: 11 October 2022

Gateway Outcome - July 2022 (115.3kB PDF)

Develop and Assess Gateway - Gateway Decision

Date added: 09 August 2022

Initial Options Appraisal Appendix Submission 2 Issue 1 (163.5kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 15 July 2022

Initial Options Appraisal Submission 2 Issue 1 (2.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 15 July 2022

Focus Engagement Group 3+4 Slides (4.3MB PDF)

Stage 2 - Engagement Evidence

Date added: 15 July 2022

Design Principle Evaluation Submission 2 Issue 1 (8.2MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 15 July 2022

Design Engagement Document (8.5MB PDF)

Stage 2 - Design Options Engagement Evidence

Date added: 15 July 2022

Focus Group 4 Minutes (947.5kB PDF)

Stage 2 - Engagement Evidence

Date added: 15 July 2022

Focus Group 3 Minutes (882.9kB PDF)

Stage 2 - Engagement Evidence

Date added: 15 July 2022

Timeline Update (182.3kB PDF)

Stage 2 - Timeline Agreement

Date added: 06 April 2022

Indicative Timeline Update - October 2021 (185.8kB PDF)

Stage 2 - Timeline Agreement

Date added: 04 November 2021

Minutes 3 Feb 21 Meeting (160.7kB PDF)

Stage 2 - Other

Date added: 27 April 2021

GAL Letter Seeking CAA Response – Stage 2 (251.5kB PDF)

Stage 2 - Other

Date added: 16 April 2021

Indicative Timeline Update March 2021 (164.9kB PDF)

Stage 2 - Timeline Agreement

Date added: 06 April 2021

MINUTES 3 MAR 2020 MEETING (129.0kB PDF)

Stage 2 - Other

Date added: 12 August 2020

Timeline Update (152.7kB PDF)

Stage 2 - Timeline Agreement

Date added: 17 July 2020

Gateway Outcome (100.5kB PDF)

Develop and Assess Gateway - Develop & Assess Gateway outcome

Date added: 28 February 2020

Focus Group 1 and 2 Presentations (7.4MB PDF)

Stage 2 - Other

Date added: 20 February 2020

Focus Group 2 Feedback (3.9MB PDF)

Stage 2 - Additional stakeholder feedback

Date added: 20 February 2020

Focus Group 1 Feedback (1.6MB PDF)

Stage 2 - Additional stakeholder feedback

Date added: 20 February 2020

Focus Group 1 and 2 Minutes (3.2MB PDF)

Stage 2 - Additional meeting minutes

Date added: 20 February 2020

Initial Options Appraisal Table Issue 1 (461.0kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 18 February 2020

Initial Options Appraisal Issue 1 (893.5kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 18 February 2020

Options Development Stage 2 Issue 1 (3.5MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 18 February 2020

Design Principles Evaluation Issue 1 (3.3MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 18 February 2020

Indicative Timeline Update Jan 2020 (132.2kB PDF)

Stage 2 - Airspace Change Proposal

Date added: 24 January 2020

Indicative Timeline Update Dec 2019 (149.2kB PDF)

Stage 2 - Other

Date added: 19 December 2019

Design Principles Review - Responses (28.0MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 24 September 2019

Design Principles Questionnaires - Responses (12.0MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 24 September 2019

Focus Group 3 Minutes - redacted (199.8kB PDF)

Stage 1 - Additional meeting minutes

Date added: 13 September 2019

Focus Group 2 Minutes - redacted (176.1kB PDF)

Stage 1 - Additional meeting minutes

Date added: 13 September 2019

Focus Group 1 Minutes - redacted (249.2kB PDF)

Stage 1 - Additional meeting minutes

Date added: 13 September 2019

Design Principles Review Response Document (237.6kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Design Principles Review (576.5kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Design Principles Questionnaires Introduction (743.1kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Design Principles Focus Groups Presentation (2.6MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Design Principles Report Issue 1 (1.5MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Gateway Dates (426.1kB PDF)

Stage 1 - Other

Date added: 28 August 2019

Response Letter from CAA to Gatwick (80.6kB PDF)

Stage 1 - Other

Date added: 08 July 2019

Response Letter from Gatwick to CAA (268.5kB PDF)

Stage 1 - Other

Date added: 08 July 2019

CAA Letter to Gatwick (92.9kB PDF)

Stage 1 - Other

Date added: 14 June 2019

Gateway Dates (426.1kB PDF)

Stage 1 - Additional meeting minutes

Date added: 02 May 2019

Assessment Meeting Presentation (531.8kB PDF)

Stage 1 - Additional meeting minutes

Date added: 07 February 2019

Assessment Meeting Minutes (558.3kB PDF)

Stage 1 - Assessment Meeting Minutes

Date added: 07 February 2019

Assessment Meeting Agenda (521.1kB PDF)

Stage 1 - Assessment Meeting Agenda

Date added: 23 January 2019

Statement of Need v1 (62.3kB PDF)

Stage 1 - Additional meeting minutes

Date added: 19 December 2018