Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is 1.

Gatwick Airport is now undertaking a new airspace change proposal involving a review and if appropriate redesign of the Route 4 SIDs taking into account the relevant aspects of the Consent Order

Close

Stage 3 : Consultation/Engagement Preparation

This step has been started

At the beginning of Stage 3 the change sponsor prepares a strategy and draft materials and submits them to the CAA, along with the full options appraisal.

CAA response to Stage 3

18th January 2024:

The revised airspace change process (CAP 1616, Version 5) will be implemented on 02 January 2024. This ACP will remain a Level 1 and will need to follow the process requirements as set out in CAP 1616 Version 5 for its scheduled Gateway in March 2024.

Close

Documents for this proposal (54 documents)

Timeline update (206.7kB PDF)

Stage 3 - Timeline Agreement

Date added: 20 March 2024

Timeline update (120.0kB PDF)

Stage 3 - Timeline Agreement

Date added: 04 March 2024

ACP Timeline Update (182.0kB PDF)

Stage 3 - Timeline Agreement

Date added: 11 July 2023

Initial Options Appraisal Assessment (272.4kB PDF)

Stage 2 - Options Appraisal Assessment (Phase I - Initial)

Date added: 31 October 2022

Initial Options Appraisal Appendix Submission 2 Issue 2 (162.6kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 26 October 2022

Initial Options Appraisal Submission 2 Issue 2 (2.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 26 October 2022

Design Principles Evaluation Submission 2 Issue 2 (8.2MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 26 October 2022

ACP-2018-86 Indicative Timelines Request September 22 (182.4kB PDF)

Stage 2 - Timeline Agreement

Date added: 11 October 2022

Gateway Outcome - July 2022 (115.3kB PDF)

Develop and Assess Gateway - Gateway Decision

Date added: 09 August 2022

Initial Options Appraisal Appendix Submission 2 Issue 1 (163.5kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 15 July 2022

Initial Options Appraisal Submission 2 Issue 1 (2.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 15 July 2022

Focus Engagement Group 3+4 Slides (4.3MB PDF)

Stage 2 - Engagement Evidence

Date added: 15 July 2022

Design Principle Evaluation Submission 2 Issue 1 (8.2MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 15 July 2022

Design Engagement Document (8.5MB PDF)

Stage 2 - Design Options Engagement Evidence

Date added: 15 July 2022

Focus Group 4 Minutes (947.5kB PDF)

Stage 2 - Engagement Evidence

Date added: 15 July 2022

Focus Group 3 Minutes (882.9kB PDF)

Stage 2 - Engagement Evidence

Date added: 15 July 2022

Timeline Update (182.3kB PDF)

Stage 2 - Timeline Agreement

Date added: 06 April 2022

Indicative Timeline Update - October 2021 (185.8kB PDF)

Stage 2 - Timeline Agreement

Date added: 04 November 2021

Minutes 3 Feb 21 Meeting (160.7kB PDF)

Stage 2 - Other

Date added: 27 April 2021

GAL Letter Seeking CAA Response – Stage 2 (251.5kB PDF)

Stage 2 - Other

Date added: 16 April 2021

Indicative Timeline Update March 2021 (164.9kB PDF)

Stage 2 - Timeline Agreement

Date added: 06 April 2021

MINUTES 3 MAR 2020 MEETING (129.0kB PDF)

Stage 2 - Other

Date added: 12 August 2020

Timeline Update (152.7kB PDF)

Stage 2 - Timeline Agreement

Date added: 17 July 2020

Gateway Outcome (100.5kB PDF)

Develop and Assess Gateway - Develop & Assess Gateway outcome

Date added: 28 February 2020

Focus Group 1 and 2 Presentations (7.4MB PDF)

Stage 2 - Other

Date added: 20 February 2020

Focus Group 2 Feedback (3.9MB PDF)

Stage 2 - Additional stakeholder feedback

Date added: 20 February 2020

Focus Group 1 Feedback (1.6MB PDF)

Stage 2 - Additional stakeholder feedback

Date added: 20 February 2020

Focus Group 1 and 2 Minutes (3.2MB PDF)

Stage 2 - Additional meeting minutes

Date added: 20 February 2020

Initial Options Appraisal Table Issue 1 (461.0kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 18 February 2020

Initial Options Appraisal Issue 1 (893.5kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 18 February 2020

Options Development Stage 2 Issue 1 (3.5MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 18 February 2020

Design Principles Evaluation Issue 1 (3.3MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 18 February 2020

Indicative Timeline Update Jan 2020 (132.2kB PDF)

Stage 2 - Airspace Change Proposal

Date added: 24 January 2020

Indicative Timeline Update Dec 2019 (149.2kB PDF)

Stage 2 - Other

Date added: 19 December 2019

Design Principles Review - Responses (28.0MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 24 September 2019

Design Principles Questionnaires - Responses (12.0MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 24 September 2019

Focus Group 3 Minutes - redacted (199.8kB PDF)

Stage 1 - Additional meeting minutes

Date added: 13 September 2019

Focus Group 2 Minutes - redacted (176.1kB PDF)

Stage 1 - Additional meeting minutes

Date added: 13 September 2019

Focus Group 1 Minutes - redacted (249.2kB PDF)

Stage 1 - Additional meeting minutes

Date added: 13 September 2019

Design Principles Review Response Document (237.6kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Design Principles Review (576.5kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Design Principles Questionnaires Introduction (743.1kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Design Principles Focus Groups Presentation (2.6MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Design Principles Report Issue 1 (1.5MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 13 September 2019

Gateway Dates (426.1kB PDF)

Stage 1 - Other

Date added: 28 August 2019

Response Letter from CAA to Gatwick (80.6kB PDF)

Stage 1 - Other

Date added: 08 July 2019

Response Letter from Gatwick to CAA (268.5kB PDF)

Stage 1 - Other

Date added: 08 July 2019

CAA Letter to Gatwick (92.9kB PDF)

Stage 1 - Other

Date added: 14 June 2019

Gateway Dates (426.1kB PDF)

Stage 1 - Additional meeting minutes

Date added: 02 May 2019

Assessment Meeting Presentation (531.8kB PDF)

Stage 1 - Additional meeting minutes

Date added: 07 February 2019

Assessment Meeting Minutes (558.3kB PDF)

Stage 1 - Assessment Meeting Minutes

Date added: 07 February 2019

Assessment Meeting Agenda (521.1kB PDF)

Stage 1 - Assessment Meeting Agenda

Date added: 23 January 2019

Statement of Need v1 (62.3kB PDF)

Stage 1 - Additional meeting minutes

Date added: 19 December 2018

Close

Potentially affected area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Close