Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is TBC.

In response to customer demand and having regard to the changes set out in the recently published Airspace Modernisation Strategy, London Oxford Airport seeks to define new GNSS based instrument flight procedures along with suitable regulated airspace in order to protect them and to facilitate safer flight conditions for all airspace users.

Close

Stage 1 : Define

This step has been started

During stage 1, the sponsor submits a statement of need, setting out the objectives of their airspace change proposal and the issues or opportunities it seeks to address. Subject to the CAA accepting that the airspace change process is the appropriate mechanism to achieve the objectives of the proposal, the sponsor will go on to develop the current-day scenario and design principles. The change sponsor will share the current-day scenario and proposed design principles with relevant stakeholders so they can comment accordingly, and take those comments into account.

CAA response to Stage 1

12/12/2023: The revised airspace change process (CAP 1616, Version 5) will be implemented on 02 January 2024. This ACP will remain a Level 1 and will need to follow the process requirements as set out in CAP 1616 Version 5.

02/11/2023: The Assessment Meeting was held on 02 November 2023. The CAA agrees that the issues identified in the Statement of Need are appropriate for consideration under the ACP process.

This ACP has provisionally been allocated as Level 1

Close

Documents for this proposal (11 documents)

Indicative Timeline - March 2024 (148.7kB PDF)

Stage 1 - Timeline Agreement

Date added: 18 March 2024

OXF-ACP-2023-033 Stage 1b -StakeholderEngagement (2.2MB PDF)

Stage 1 - Design Principles

Date added: 13 March 2024

Timeline (259.6kB PDF)

Stage 1 - Timeline Agreement

Date added: 24 November 2023

DAP1916V2-938-Receipt-SON_V4-Redacted (874.3kB PDF)

Stage 1 - Statement of Need

Date added: 16 November 2023

Assessment Meeting PowerPoint Presentation (1.4MB PDF)

Stage 1 - Other

Date added: 16 November 2023

Stage 1 Permanent ACP Assessment Meeting Minutes_Redacted (248.7kB PDF)

Stage 1 - Assessment Meeting Minutes

Date added: 16 November 2023

Stage 1 Permanent ACP Assessment Meeting Agenda (44.5kB PDF)

Stage 1 - Assessment Meeting Agenda

Date added: 31 October 2023

Statement of Need V3 (74.4kB PDF)

Stage 1 - Statement of Need

Date added: 21 September 2023

20230920-Confirmation Statement (84.1kB PDF)

Stage 1 - Other

Date added: 20 September 2023

Statement of Need V2 (71.0kB PDF)

Stage 1 - Statement of Need

Date added: 19 June 2023

Statement of Need (69.1kB PDF)

Stage 1 - Statement of Need

Date added: 11 May 2023

Close

Potentially affected area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Close