11/09/2024: Until the final iteration of the airspace change masterplan including the updated programme plan has been developed, the full indicative timeline for this ACP, which must be aligned with the updated programme plan, cannot be confirmed. The Gateways within the published document 'Indicative Timeline – September 2024' are subject to change.
12/12/2023: The revised airspace change process (CAP 1616, Version 5) will be implemented on 02 January 2024. This ACP will remain a Level 1 and will need to follow the process requirements as set out in CAP 1616 Version 5.
01/08/2023: The CAA has completed the Develop and Assess Gateway Assessment and is not satisfied that the change sponsor has met the requirements of the Process up to this point. The CAA does not approve progress to the next Step. Further explanation for this decision is contained in 'Develop & Assess Gateway Outcome- July 2023'.
09/05/2023: Until iteration three of the airspace change masterplan, including the updated programme plan has been assessed and accepted by the CAA and Department for Transport as co sponsors of airspace modernisation, the full indicative timeline for this ACP cannot be confirmed. The Gateways within the published document 'Indicative Timeline - May 2023' are subject to change.
04/03/2023: The CAA has completed the Develop and Assess Gateway Assessment and is not satisfied that the change sponsor has met the requirements of the Process up to this point. The CAA does not approve progress to the next Step. Further explanation for this decision is contained in the published document 'Develop & Assess Gateway Outcome- March 2023'.
In accordance with direction 5(1) of the Civil Aviation Authority (Air Navigation) Directions 2017 (as amended), the CAA is not satisfied this airspace change proposal up to this stage has demonstrated that it is in accordance with the CAA’s Airspace Modernisation Strategy (CAP 1711), including Iteration 2 of the UK Masterplan that has been accepted into it.
21/11/2022: Until iteration three of the airspace change masterplan, including the updated programme plan has been assessed and accepted by the CAA and Department for Transport as co sponsors of airspace modernisation, the full indicative timeline for this ACP cannot be confirmed. The Gateways within the published document 'Indicative Timeline - November 2022' are subject to change.
16/09/2022: The CAA has completed the Develop and Assess Gateway Assessment and is not satisfied that the change sponsor has met the requirements of the Process up to this point. The CAA does not approve progress to the next Step. Further explanation for this decision is contained in the published document 'Develop & Assess Gateway Outcome- September 2022'.
In accordance with direction 5(1) of the Civil Aviation Authority (Air Navigation) Directions 2017 (as amended), the CAA is not satisfied this airspace change proposal up to this stage has demonstrated that it is in accordance with the CAA’s Airspace Modernisation Strategy (CAP 1711), including Iteration 2 of the UK Masterplan that has been accepted into it.
01/04/2022: The CAA has completed the Develop and Assess Gateway Assessment and is not satisfied that the change sponsor has met the requirements of the Process up to this point. The CAA does not approve progress to the next Step. Further explanation for this decision is contained in the published document 'Develop & Assess Gateway Outcome- March 2022'.
In accordance with direction 5(1) of the Civil Aviation Authority (Air Navigation) Directions 2017 (as amended), the CAA is not satisfied this airspace change proposal up to this stage has demonstrated that it is in accordance with the CAA’s Airspace Modernisation Strategy (CAP 1711), including Iteration 2 of the UK Masterplan that has been accepted into it.