Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is 1.

Optimal alignment and connectivity of the ATS route network with each airport's airspace structures.

This change is part of the Future Airspace Strategy Implementation South programme (FASI-S) and accords with the UK's Airspace Modernisation Strategy (AMS).

Close

Stage 3 : Consultation/Engagement Preparation

This step has been started

At the beginning of Stage 3 the change sponsor prepares a strategy and draft materials and submits them to the CAA, along with the full options appraisal.

CAA response to Stage 3

13/12/2023 - The revised airspace change process (CAP 1616, Version 5) will be implemented on 02 January 2024. This ACP will remain a Level 1 and will need to follow the process requirements as set out in CAP 1616 Version 5.

18/03/2024: Until iteration three of the airspace change masterplan, including the updated programme plan has been assessed and accepted by the CAA and Department for Transport as co sponsors of airspace modernisation, the full indicative timeline for this ACP cannot be confirmed. The Gateways within the published document 'Indicative Timeline - March 2024' are subject to change.

Close

Documents for this proposal (71 documents)

LTMA St 3 Early Engagement - Position Report Oct 2023 (7.3MB PDF)

Stage 3 - Engagement Material

Date added: 03 April 2024

LTMA St 3 Early Engagement response document (591.0kB PDF)

Stage 3 - Engagement Evidence

Date added: 03 April 2024

Indicative Timeline - March 2024 (211.7kB PDF)

Stage 3 - Timeline Agreement

Date added: 18 March 2024

CAA Initial Options Appraisal Assessment (1.1MB PDF)

Stage 2 - Options Appraisal Assessment (Phase I - Initial)

Date added: 05 June 2023

St2-Airports-Stansted-Module Issue 1.3 (1.5MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Southend-Module Issue 1.3 (1.1MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Southampton-Module Issue 1.3 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Northolt-Module Issue 1.3 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Manston-Module Issue 1.3 (651.8kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Luton-Module Issue 1.3 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-LondonCity-Module Issue 1.3 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Heathrow-Module Issue 1.3 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Gatwick-Module Issue 1.3 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Farnborough-Module Issue 1.3 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-Bournemouth-Module Issue 1.3 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2-Airports-BigginHill-Module Issue 1.3 (1.3MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St2 LTMA Master and Network Issue 1.3 (2.7MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 02 June 2023

St 2 Engagement Evidence - feedback responses (399.3kB PDF)

Stage 2 - Engagement Evidence

Date added: 30 May 2023

St 2 Airport - Stansted Module Issue 1.2 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Southend Module Issue 1.2 (1.1MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Southampton Module Issue 1.2 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Northolt Module Issue 1.2 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Manston Module Issue 1.2 (630.3kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Luton Module Issue 1.2 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - London City Module Issue 1.2 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Heathrow Module Issue 1.2 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Gatwick Module Issue 1.2 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Farnborough Module Issue 1.2 (1.1MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Bournemouth Module Issue 1.2 (1.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

St 2 Airport - Biggin Hill Module Issue 1.2 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

LTMA St 2 Master and Network Issue 1.2 (2.6MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 30 May 2023

CAA's Clarification Questions and NATS' Response (295.3kB PDF)

Stage 2 - Other

Date added: 10 May 2023

St2 Airport - Stansted Module Issue 1.1 (6.3MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Southend Module Issue 1.1 (5.5MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Southampton Module Issue 1.1 (8.8MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Northolt Module Issue 1.1 (8.9MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Manston Module Issue 1.1 (3.7MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Luton Module Issue 1.1 (5.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - London City Module Issue 1.1 (6.3MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Heathrow Module Issue 1.1 (8.5MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Gatwick Module Issue 1.1 (6.8MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Farnborough Module Issue 1.1 (4.6MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Bournemouth Module Issue 1.1 (6.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2 Airport - Biggin Hill Module Issue 1.1 (6.9MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

LTMA St2 Master and Network Issue 1.1 (10.8MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 09 May 2023

St2-LTMA-ExampleEngagementPack (11.0MB PDF)

Stage 2 - Engagement Evidence

Date added: 24 February 2023

St2-Airports-Stansted-Module Issue 1.0 (1.3MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Southend-Module Issue 1.0 (952.6kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Southampton-Module Issue 1.0 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Northolt-Module Issue 1.0 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Manston-Module Issue 1.0 (490.7kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Luton-Module Issue 1.0 (878.0kB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-LondonCity-Module Issue 1.0 (1.0MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Heathrow-Module Issue 1.0 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Gatwick-Module Issue 1.0 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Farnborough-Module Issue 1.0 (1.0MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-Bournemouth-Module Issue 1.0 (1.2MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

St2-Airports-BigginHill-Module Issue 1.0 (1.1MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

LTMA St2 Master and Network Issue 1.0 (2.4MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 24 February 2023

Indicative Timeline - November 2022 (301.8kB PDF)

Stage 2 - Timeline Agreement

Date added: 16 November 2022

Indicative Timeline - June 2022 (206.5kB PDF)

Stage 2 - Timeline Agreement

Date added: 20 June 2022

Indicative Timeline - July 2021 (206.7kB PDF)

Stage 2 - Timeline Agreement

Date added: 09 July 2021

Design Principles (546.8kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 04 June 2020

Assessment Meeting Minutes (412.3kB PDF)

Stage 1 - Assessment Meeting Minutes

Date added: 04 June 2020

Assessment Meeting Presentation (3.8MB PDF)

Stage 1 - Other

Date added: 04 June 2020

Assessment Meeting Agenda (564.9kB PDF)

Stage 1 - Assessment Meeting Agenda

Date added: 04 June 2020

Statement of Need v2 (530.0kB PDF)

Stage 1 - Statement of Need

Date added: 04 June 2020

Statement of Need (80.8kB PDF)

Stage 1 - Statement of Need

Date added: 04 June 2020

Close

Potentially affected area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Close