Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is M1. The detailed process requirements are published in Part 1 of CAP 1616.

Approval is sought for a Permanent Airspace Change surrounding Keevil Airfield, a satellite aerodrome of RAF Brize Norton located North

West of the Salisbury Plain Danger Areas. Airspace is required to facilitate Beyond Visual Line of Sight (BVLOS) operation of military

Unmanned Air Systems.

Operating from Keevil will allow for essential aircrew and groundcrew training in an environment that is currently not possible from other

UK locations. The airfield will be primarily used for launch and recovery into EG D123 (2NM to the South), the principal operating

airspace already utilised for military BVLOS activity.

CAA response to Step 3c

Documents for this proposal (31 documents)

Timeline Change Request

Consult Gateway - Timeline Agreement

Date added: 17 May 2022 19:40

CAA Full Options Appraisal Assessment

Step 3b - Options Appraisal Assessment (Phase II - Full)

Date added: 01 June 2022 08:40

Consultation FAQs

Step 3b - Other

Date added: 01 June 2022 08:11

Stage 3 Environmental Impact Assessment

Step 3b - Other

Date added: 01 June 2022 08:10

Electronic Conspicuity Flight Data

Step 3b - Other

Date added: 01 June 2022 08:09

Full Options Appraisal

Step 3b - Options Appraisal (Phase II - Full)

Date added: 01 June 2022 08:08

Consultation Strategy

Step 3b - Consultation Strategy

Date added: 01 June 2022 08:07

Consultation Document

Step 3b - Other

Date added: 01 June 2022 08:06

CAA Letter - Navigation Warnings

Step 3a - Engagement Evidence

Date added: 28 April 2022 08:47

Initial Options Appraisal Assessment

Develop & Assess Gateway - Gateway Decision

Date added: 14 March 2022 10:42

Initial Options Appraisal v2

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 02 March 2022 14:02

Initial Options Appraisal v1

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 28 February 2022 16:23

Initial Safety Assessment

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 28 February 2022 16:13

Environmental Impact Assessment

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 28 February 2022 16:13

Meeting minutes - BGA & local gliding club

Step 2a - Engagement Evidence

Date added: 28 February 2022 16:11

Meeting minutes - local GA pilot

Step 2a - Engagement Evidence

Date added: 28 February 2022 16:09

Stage 2 Engagement Evidence

Step 2a - Engagement Evidence

Date added: 28 February 2022 16:06

Design Options Feedback

Step 2a - Design Options Engagement Evidence

Date added: 28 February 2022 16:04

Stage 2A Engagement Methodology

Step 2a - Other

Date added: 28 February 2022 16:03

Stage 2A Design Principle Evaluation

Step 2a - Design Principle Evaluation

Date added: 09 February 2022 16:15

Stage 2A Design Options Annex A - Feedback Form

Step 2a - Design Options

Date added: 21 January 2022 08:11

Stage 2A Design Options

Step 2a - Design Options

Date added: 21 January 2022 08:11

Gateway Submission Follow Up

Define Gateway - Other

Date added: 04 January 2022 12:09

Stage 1 Gateway Documentation

Step 1b - Design Principles

Date added: 09 December 2021 08:59

Design Principles Engagement Letter

Step 1b - Design Principles Engagement Evidence

Date added: 09 December 2021 08:58

Timeline

Step 1a - Timeline Agreement

Date added: 14 October 2021 15:47

Assessment Meeting Minutes - Redacted

Step 1a - Assessment Meeting Minutes

Date added: 01 October 2021 15:13

Statement of Need v2

Step 1a - Statement of Need

Date added: 21 September 2021 10:26

Statement of Need

Step 1a - Statement of Need

Date added: 21 September 2021 10:26

Assessment Meeting Presentation

Step 1a - Other

Date added: 17 September 2021 07:03

Assessment Meeting Agenda

Step 1a - Assessment Meeting Agenda

Date added: 17 September 2021 07:02

Close

Potentially Affected Area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Step 3c : Commence Consultation

This step has been started

At the Commence Consultation Step, the change sponsor implements its consultation strategy and launches the consultation.