Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is 1.

This airspace change intends to modernise airspace around Aberdeen Airport in order to:

- Meet the regulatory requirements for Performance Based Navigation (PBN) implementation relevant to arrivals

- Decouple existing procedures from ground based navigational aids

- Meet the intent of the UK's Airspace Modernisation Strategy

Close

Stage 4 : Update and Submit

This step has been started

During Stage 4, the change sponsor will select a final design option and consider updating it in light of information received during the consultation or engagement. The change sponsor will also conduct the final options appraisal, assess the need for additional consultation or engagement, and submit the final proposal to the CAA.

Documents for this proposal (41 documents)

Consultation Response Categorisation Document Vn 1.1 (4.3MB PDF)

Stage 3 - Consultation Evidence

Date added: 11 October 2024

Consultation Summary Document (1.1MB PDF)

Stage 3 - Consultation Material

Date added: 29 April 2024

Main Consultation Document (5.1MB PDF)

Stage 3 - Consultation Material

Date added: 29 April 2024

Glossary & Terminology Document (302.7kB PDF)

Stage 3 - Consultation Material

Date added: 29 April 2024

Frequently Asked Questions (Version 1 April 2024) (298.3kB PDF)

Stage 3 - Consultation Material

Date added: 29 April 2024

Full Options Appraisal (5.6MB PDF)

Stage 3 - Options Appraisal (Phase II - Full)

Date added: 29 April 2024

FOA - Technical Appendix (13.8MB PDF)

Stage 3 - Other

Date added: 29 April 2024

Consultation Strategy (1.2MB PDF)

Stage 3 - Consultation Strategy

Date added: 29 April 2024

CAA Full Options Appraisal Assessment (973.4kB PDF)

Stage 3 - Options Appraisal Assessment (Phase II - Full)

Date added: 19 March 2024

Revised Statement of Need (75.4kB PDF)

Stage 1 - Statement of Need

Date added: 16 October 2023

Indicative Timeline - October 2023 (361.4kB PDF)

Stage 3 - Timeline Agreement

Date added: 02 October 2023

Indicative Timeline - Sept 2023 (216.6kB PDF)

Stage 3 - Timeline Agreement

Date added: 15 September 2023

Indicative Timeline - April 2023 (395.7kB PDF)

Stage 3 - Timeline Agreement

Date added: 17 April 2023

Indicative Timeline - January 2023 (252.8kB PDF)

Stage 3 - Timeline Agreement

Date added: 23 January 2023

CAA Initial Options Appraisal Assessment (7.4MB PDF)

Stage 2 - Options Appraisal Assessment (Phase I - Initial)

Date added: 05 January 2023

Step 2A DPE Annex A V1.1 (2.1MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 20 December 2022

Step 2B Initial Options Appraisal V1.1 (6.0MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 20 December 2022

Step 2B Initial Options Appraisal - Technical Appendix B V1 (6.2MB PDF)

Stage 2 - Engagement Evidence

Date added: 18 November 2022

Step 2B Initial Options Appraisal V1 (5.9MB PDF)

Stage 2 - Options Appraisal (Phase I - Initial)

Date added: 18 November 2022

Step 2A Appendix F - Stakeholder Presentation V1 (3.9MB PDF)

Stage 2 - Engagement Evidence

Date added: 18 November 2022

Step 2A Appendix E - Stakeholder Resources V1 (4.7MB PDF)

Stage 2 - Engagement Evidence

Date added: 18 November 2022

Step 2A Appendix D - Feedback V1 (211.7kB PDF)

Stage 2 - Engagement Evidence

Date added: 18 November 2022

Step 2A Appendix C - Engagement Details V1 (21.1MB PDF)

Stage 2 - Engagement Evidence

Date added: 18 November 2022

Step 2A Appendix B - Engagement Log V1 (1.1MB PDF)

Stage 2 - Engagement Evidence

Date added: 18 November 2022

Step 2A Appendix A - Stakeholder List V1 (270.8kB PDF)

Stage 2 - Engagement Evidence

Date added: 18 November 2022

Step 2A DPE Annex A V1 (2.1MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 18 November 2022

Step 2A DPE Report V1 (4.2MB PDF)

Stage 2 - Design Principle Evaluation

Date added: 18 November 2022

Indicative Timeline - June 2022 (206.2kB PDF)

Stage 2 - Timeline Agreement

Date added: 27 June 2022

Indicative Timeline - August 2021 (145.3kB PDF)

Stage 2 - Timeline Agreement

Date added: 06 August 2021

Appendix A - Engagement Log V1 (5.2MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 30 March 2020

Appendix C - Stakeholder Feedback V1 (1.6MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 30 March 2020

Appendix D - Focus Group Research V1 (1.1MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 27 March 2020

Appendix B - Engagement Material V1 (2.2MB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 27 March 2020

Report on airspace design principles engagement V1 (643.0kB PDF)

Stage 1 - Design Principles Engagement Evidence

Date added: 27 March 2020

Assessment Meeting Minutes (318.7kB PDF)

Stage 1 - Assessment Meeting Minutes

Date added: 02 December 2019

Assessment meeting agenda (18.6kB PDF)

Stage 1 - Assessment Meeting Agenda

Date added: 12 November 2019

Statement of Need (103.3kB PDF)

Stage 1 - Statement of Need

Date added: 12 November 2019

Close

Potentially affected area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.