Decide Gateway

This step has been started

At the Decide Gateway, the CAA reviews and signs-off the documentation relating to Stage 5.

Purpose of this change

Although called an airspace change, this is simply designing a defined approach procedure for the jet aircraft and commercial helicopters (from small helicopters and business jets to larger airliners) to follow to land at the airport. Currently, these aircraft's pilots define their own approach, which cannot be regularised and means we can provide no altitude safeguards and defined arrival routes to both other airspace users and local communities. This ACP will design and implement internationally recognised approved approach routes and landing procedures for Kemble's runway 26 and runway 08.

Potentially Affected Area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Documents for this proposal (72 documents)

Design Change Supplementary Document

Step 5b - Other

Date added: 11 December 2020 09:24

No Hold Additional Justification Document

Step 5b - Other

Date added: 10 December 2020 16:28

Enclosure 2 (Updated V2) to Formal Submission Document

Step 4b - Airspace Change Proposal

Date added: 21 August 2020 11:30

Enclosure 1 (Updated V2) (Safety Case) to Formal Submission Document

Step 4b - Airspace Change Proposal

Date added: 21 August 2020 11:26

Annex G (V2 ) Updated to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 21 August 2020 11:21

Annex F (V2 ) Updated to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 21 August 2020 11:20

Annex E (V2 ) Updated to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 21 August 2020 11:19

Annex B (v2 Updated) to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 21 August 2020 11:15

Formal Proposal Submission Main Document V2

Step 4b - Airspace Change Proposal

Date added: 21 August 2020 11:10

Enclosure 3 to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 14:02

Enclosure 2 to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 14:01

Enclosure 1 to Safety Case

Step 4b - Safety assessment 

Date added: 17 July 2020 14:00

Enclosure 1 (Safety Case) to Formal Proposal

Step 4b - Safety assessment 

Date added: 17 July 2020 13:59

Annex G to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:58

Annex F to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:57

Annex E to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:57

Annex D to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:56

Annex C to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:55

Annex B to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:55

Annex A-2 to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:54

Annex A-1 to Formal Proposal Submission

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:54

Formal Proposal Submission Main Document

Step 4b - Airspace Change Proposal

Date added: 17 July 2020 13:52

Consultation Response Document V2 Updated 20 Aug 20

Step 4a - Consultation Response Document

Date added: 21 August 2020 10:41

Step 4a Updated Airspace Options Designs

Step 4a - Design Options

Date added: 12 June 2020 10:23

Annex F to Consultation Review Document

Step 4a - Consultation Response Document

Date added: 12 June 2020 10:21

Annex D to Consultation Review Document

Step 4a - Consultation Response Document

Date added: 12 June 2020 10:20

Annex B to Consultation Review Document

Step 4a - Consultation Response Document

Date added: 12 June 2020 10:20

Annex A To Consultation Review Document

Step 4a - Consultation Response Document

Date added: 12 June 2020 10:19

Kemble Consultation Review Document

Step 4a - Consultation Response Document

Date added: 12 June 2020 10:18

Kemble Options Appraisal (Final)

Step 4a - Options Appraisal (Phase III - Final)

Date added: 12 June 2020 10:17

Categoriation and Review of Consultation Responses

Step 3d - Consultation Response Document

Date added: 22 May 2020 09:23

Consultation Record

Step 3d - Additional meeting minutes

Date added: 22 May 2020 09:16

Consultation Strategy

Step 3c - Consultation Strategy

Date added: 09 February 2020 21:17

Full Options Appraisal

Step 3c - CAA Options Appraisal Assessment (Phase II - Full)

Date added: 09 February 2020 09:20

Consultation Strategy

Step 3c - Consultation Strategy

Date added: 09 February 2020 09:17

Full Options Appraisal

Step 3c - Options Appraisal (Phase II - Full)

Date added: 09 February 2020 09:16

Cotswold Airport Consultation Document

Step 3c - Other

Date added: 09 February 2020 09:05

Full Options Appraisal

Step 3c - CAA Options Appraisal Assessment (Phase II - Full)

Date added: 09 February 2020 09:04

Consultation Strategy

Step 3c - Consultation Strategy

Date added: 09 February 2020 09:03

Consultation Strategy

Step 3c - Consultation Strategy

Date added: 09 February 2020 08:55

Full Options Appraisal

Step 3c - CAA Options Appraisal Assessment (Phase II - Full)

Date added: 09 February 2020 08:48

Cotswold Airport Consultation Document

Step 3c - Other

Date added: 09 February 2020 08:44

Cotswold Airport Consultation Document

Step 3c - Consultation Assessment

Date added: 09 February 2020 08:39

CAA Statement

Consult Gateway - Consult Gateway outcome

Date added: 04 July 2019 13:28

CAA Options Appraisal Assessment (Phase II Full)

Step 3b - Options Appraisal (Phase II - Full)

Date added: 28 February 2020 10:01

Option Appraisal (Phase II - Full) (Sponsor)

Step 3b - Options Appraisal (Phase II - Full)

Date added: 28 February 2020 09:17

Consultation Document

Step 3b - Other

Date added: 10 February 2020 18:09

Consultation Strategy

Step 3b - Consultation Strategy

Date added: 10 February 2020 18:07

Change Approval for Kemble's ACP Timeline

Step 3a - Airspace change extension justification 

Date added: 03 April 2019 10:24

Step 2b Initial Options Aporaisal Comparison Table

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 07 February 2019 13:37

Step 2b Initial Options Appraisal (Phase 1)

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 07 February 2019 13:35

Step 2a Engagement Methodology Review

Step 2a - Additional meeting minutes

Date added: 18 February 2019 10:04

Step 2a Design Principles Options Evaluation

Step 2a - Design Principle Evaluation

Date added: 08 February 2019 17:30

Step 2a Kemble Design Options Brize Norton TELECON

Step 2a - Additional meeting minutes

Date added: 07 February 2019 13:33

Step 2a Kemble Design Options Glider Meeting

Step 2a - Additional meeting minutes

Date added: 07 February 2019 13:32

Step 2a Kemble Design Options Engagement Feedback

Step 2a - Additional meeting minutes

Date added: 07 February 2019 13:31

Step 2a Kemble Design Options (and Engagement)

Step 2a - Design Options

Date added: 07 February 2019 13:21

Enclosure 3 to Design Principles Supplementary Doc

Step 1b - Other

Date added: 18 October 2018 10:49

Enclosure 2 to Design Principles Supplementary Doc

Step 1b - Other

Date added: 18 October 2018 10:49

Enclosure 1 to Design Principles Supplementary Doc

Step 1b - Other

Date added: 18 October 2018 10:48

Appendix E Final Design Principles

Step 1b - Other

Date added: 18 October 2018 10:43

Annex D

Step 1b - Other

Date added: 18 October 2018 10:41

Annex C

Step 1b - Other

Date added: 18 October 2018 10:40

Annex B

Step 1b - Other

Date added: 18 October 2018 10:40

Annex A

Step 1b - Other

Date added: 18 October 2018 10:38

Kemble Aerodrome Airspace Change Proposal

Step 1b - Airspace Change Proposal

Date added: 18 October 2018 10:32

Assessment review meeting

Step 1a - Other

Date added: 27 September 2018 13:17

Assessment meeting minutes

Step 1a - Assessment Meeting Minutes

Date added: 27 September 2018 13:15

Assessment meeting agenda

Step 1a - Assessment Meeting Agenda

Date added: 27 September 2018 13:14

Statement of Need v3

Step 1a - Statement of Need

Date added: 27 September 2018 13:12

Statement of Need V2

Step 1a - Statement of Need

Date added: 27 September 2018 13:08

Statement of Need

Step 1a - Statement of Need

Date added: 27 September 2018 13:04

Close

CAA response to Decide Gateway

[22 Dec 2020] The CAA has completed the Decide Gateway Assessment and is satisfied that the change sponsor has met the requirements of the Airspace Change Process. The CAA approves the implementation of this airspace change proposal for the reasons and on the conditions set out in the regulatory decision document.