Purpose of this change

This proposal is for a Permanent change to the notified airspace design, and the change level is 1. The detailed process requirements are published in Part 1 of CAP 1616.

Snowdonia Aerospace LLP is seeking to provide an environment for safe operation of all ongoing aerospace-related Research, Development, Test and Evaluation (RDT&E) activities in the vicinity of Llanbedr Airfield and the ability for associated aircraft to transit safely to/from Danger Area D201 to undertake extended range/endurance/altitude testing without concern for other air traffic.

CAA response to Step 6

Documents for this proposal (70 documents)

CAA Decision Document Issue 2

Decide Gateway - Gateway Decision

Date added: 21 September 2021 08:51

CAA Decision Document

Decide Gateway - Gateway Decision

Date added: 13 August 2021 09:54

CAA Operational Assessment

Step 5b - Operational Assessment

Date added: 08 June 2021 07:47

CAA Consultation Assessment

Step 5b - Consultation Assessment

Date added: 08 June 2021 07:46

CAA Environmental Assessment

Step 5b - Environmental Assessment

Date added: 08 June 2021 07:46

CAA Final Options Appraisal Assessment

Step 5b - Options Appraisal Assessment (Phase III - Final)

Date added: 08 June 2021 07:45

Llanbedr DA ACP Annex 4 Issue 2.1 (minor edit)

Step 4b - Other

Date added: 08 June 2021 07:38

Llanbedr DA ACP - Draft Letter of Agreement

Step 4b - Engagement Evidence

Date added: 04 June 2021 16:31

Llanbedr DA Airspace Change Proposal Issue 2.1 (minor edit)

Step 4b - Airspace Change Proposal

Date added: 04 June 2021 16:29

Llanbedr DA ACP Annex 4 Issue 2

Step 4b - Other

Date added: 26 March 2021 08:55

Llanbedr DA ACP Annex 9

Step 4b - Airspace Change Proposal

Date added: 22 February 2021 12:01

Llanbedr DA ACP Annex 8

Step 4b - Other

Date added: 22 February 2021 12:00

Llanbedr DA Airspace Change Proposal Issue 2

Step 4b - Airspace Change Proposal

Date added: 22 February 2021 10:28

Llanbedr DA ACP Annex 7

Step 4b - Engagement Evidence

Date added: 11 February 2021 10:04

Llanbedr DA ACP Annex 6

Step 4b - Other

Date added: 11 February 2021 10:02

Llanbedr DA ACP Annex 5

Step 4b - Other

Date added: 11 February 2021 10:01

Llanbedr DA ACP Annex 4

Step 4b - Other

Date added: 11 February 2021 10:01

Llanbedr DA ACP Annex 3

Step 4b - Other

Date added: 11 February 2021 10:00

Llanbedr DA ACP Annex 2

Step 4b - Engagement Evidence

Date added: 11 February 2021 09:59

Llanbedr DA ACP Annex 1

Step 4b - Other

Date added: 11 February 2021 09:58

Llanbedr DA Airspace Change Proposal

Step 4b - Airspace Change Proposal

Date added: 11 February 2021 09:57

Llanbedr DA Consultation Review Annex 4 Issue 2

Step 4a - Other

Date added: 04 June 2021 16:27

Llanbedr DA Consultation Review Annex 5 Issue 2

Step 4a - Other

Date added: 04 June 2021 16:26

Llanbedr DA Revised Design Issue 1.1 (minor edit)

Step 4a - Other

Date added: 04 June 2021 16:24

Llanbedr DA Consultation Review & Response Categorisation Issue 2

Step 4a - Consultation Response Document

Date added: 04 June 2021 16:20

Llanbedr DA Final Options Appraisal Issue 2.1 (minor edit)

Step 4a - Options Appraisal (Phase III - Final)

Date added: 04 June 2021 16:18

Llanbedr DA Final Options Appraisal Issue 2

Step 4a - Options Appraisal (Phase III - Final)

Date added: 26 March 2021 08:54

Llanbedr DA Revised Design

Step 4a - Other

Date added: 11 February 2021 09:56

Llanbedr DA Final Options Appraisal

Step 4a - Options Appraisal (Phase III - Final)

Date added: 11 February 2021 09:55

Llanbedr DA Consultation Review Annex 5

Step 4a - Other

Date added: 11 February 2021 09:54

Llanbedr DA Consultation Review Annex 4

Step 4a - Engagement Evidence

Date added: 11 February 2021 09:53

Llanbedr DA Consultation Review Annex 3

Step 4a - Engagement Evidence

Date added: 11 February 2021 09:52

Llanbedr DA Consultation Review Annex 2

Step 4a - Engagement Evidence

Date added: 11 February 2021 09:50

Llanbedr Consultation Review Annex 1

Step 4a - Engagement Evidence

Date added: 11 February 2021 09:49

Llanbedr DA Consultation Review & Response Categorisation

Step 4a - Consultation Response Document

Date added: 11 February 2021 09:47

Llanbedr DA Full Options Appraisal Assessment

Step 3b - Options Appraisal Assessment (Phase II - Full)

Date added: 01 December 2020 16:00

Llanbedr DA Full Options Appraisal

Step 3b - Options Appraisal (Phase II - Full)

Date added: 01 December 2020 15:59

Llanbedr DA Environmental Scaling Justification

Step 3b - Other

Date added: 01 December 2020 15:58

Llanbedr DA Consultation Document

Step 3b - Consultation Strategy

Date added: 01 December 2020 15:57

Llanbedr DA Consultation Strategy

Step 3b - Consultation Strategy

Date added: 01 December 2020 15:53

Llanbedr DA Consultation Document Easy Read Guide

Step 3b - Consultation Strategy

Date added: 01 December 2020 15:52

Llanbedr DA Revised Timeline Agreement

Step 3a - Timeline Agreement

Date added: 01 December 2020 15:50

Llanbedr DA Revised Timeline Agreement

Step 3a - Timeline Agreement

Date added: 02 September 2020 14:18

Llanbedr DA Follow-up Letter to Stakeholders Welsh Version

Step 2b - Engagement Evidence

Date added: 28 August 2020 17:38

Llanbedr DA Follow-up Letter to Stakeholders

Step 2b - Engagement Evidence

Date added: 28 August 2020 17:37

Llanbedr DA Follow-up Letter to Individual Stakeholder 04

Step 2b - Engagement Evidence

Date added: 28 August 2020 17:36

Llanbedr DA Follow-up Letter to Individual Stakeholder 03

Step 2b - Engagement Evidence

Date added: 28 August 2020 17:36

Llanbedr DA Follow-up Letter to Individual Stakeholder 02

Step 2b - Engagement Evidence

Date added: 28 August 2020 17:35

Llanbedr DA Follow-up Letter to Individual Stakeholder 01

Step 2b - Engagement Evidence

Date added: 28 August 2020 17:35

Llanbedr DA 2B Initial Options Appraisal Assessment

Step 2b - Options Appraisal Assessment (Phase I - Initial)

Date added: 28 August 2020 17:15

Llanbedr DA 2B Initial Options Appraisal

Step 2b - Options Appraisal (Phase I - Initial)

Date added: 28 August 2020 17:03

Llanbedr DA 2A Design Options & DP Evaluation V3

Step 2a - Design Options

Date added: 28 August 2020 16:55

Llanbedr DA 2A Design Options & DP Evaluation V2

Step 2a - Design Options

Date added: 28 August 2020 16:53

Llanbedr DA 2A Annex 1 Engagement Evidence

Step 2a - Design Options Engagement Evidence

Date added: 28 August 2020 16:52

Llanbedr DA 2A Design Options & DP Evaluation

Step 2a - Design Options

Date added: 28 August 2020 16:49

Llanbedr DA 1B Design Principles Report V3

Step 1b - Design Principles

Date added: 24 August 2020 10:15

Llanbedr DA Revised Timeline Agreement

Step 1b - Timeline Agreement

Date added: 10 August 2020 20:47

Llanbedr DA 1B Design Principles Report V2

Step 1b - Design Principles

Date added: 10 August 2020 20:26

Llanbedr DA 1B Annex 1 DPs Supporting Evidence

Step 1b - Design Principles Engagement Evidence

Date added: 16 July 2020 12:20

Llanbedr DA 1B Design Principles Report

Step 1b - Design Principles

Date added: 16 July 2020 12:17

Llanbedr Airspace Statement of Need Issue 1 2019

Step 1a - Statement of Need

Date added: 11 May 2020 07:42

Llanbedr DA Justification for Scaling

Step 1a - Other

Date added: 01 May 2020 09:10

Llanbedr DA Timeline

Step 1a - Other

Date added: 01 May 2020 09:06

Llanbedr DA Assessment Meeting Presentation

Step 1a - Other

Date added: 13 February 2020 14:14

Llanbedr Danger Area Assessment Meeting Minutes

Step 1a - Assessment Meeting Minutes

Date added: 13 February 2020 14:10

Llanbedr Danger Area Assessment Meeting Agenda

Step 1a - Assessment Meeting Agenda

Date added: 22 January 2020 15:53

Llanbedr Danger Area Statement of Need Issue 2

Step 1a - Statement of Need

Date added: 22 January 2020 15:52

Llanbedr Airspace Initial Meeting Minutes

Step 1a - Additional meeting minutes

Date added: 22 January 2020 15:51

Llanbedr Airspace Initial Meeting Presentation

Step 1a - Other

Date added: 22 January 2020 15:50

Llanbedr Airspace Initial Meeting Agenda

Step 1a - Assessment Meeting Agenda

Date added: 22 January 2020 15:49

Close

Potentially Affected Area

This is the area which may be affected by this airspace change depending on its development. This area may change as the proposal is developed.

Step 6 : Implement

This step has been started

During the Implement Step, the change sponsor implements the approved change, working with air navigation service providers as necessary.